Sl.No |
Name of Project/Work |
Percentage of participation of Bidder in the Project |
Date of start |
Value of contract as per Agreement/LOA Rs. In Crores |
Construction period as per Agreement/LOA |
Value of work completed in Rs. Crores |
Balance value of work to be completed Rs. in Crores |
Anticipated date of completion |
Balance value of work at 2021-22/21 price level Rs. In Crores |
1 |
Construction of Major Bridge (24x18.3m Span) Viaduct at Ch.39050m on Mahekari river in Connection with Ahmednagar-Beed-Parli Vaijnath New BG line |
100 |
8/1/2017 |
36.84 |
24 Months |
33.81 |
3.03 |
3/31/2022 |
3.64 |
2 |
Water Resources Department-BRR Vamsadhara Project-Phase-II of Stage II-Supplementation to the Command under Narayanapuram anicut by excavating High Level Canal taking off from Km5.600 of Hiramandalam Reservoir earth dam to connect the tail end on upstream of Narayanapuram Anicut of Srikakulam District including formation of distributory network for 5,000 acres of new ayacut |
100 |
8/9/2017 |
78.98 |
12 Months |
46.84 |
32.14 |
5/31/2022 |
40.18 |
3 |
Earthwork in embankment, cutting and bridge approaches and Construction of minor bridges and RUBs in the section between Beed to Parli form Ch. 210000 to 230000 m for Ahmednagar-Beed-Parli Vaijnath New Broad Gauge line project. |
100 |
3/9/2018 |
99.88 |
24 Months |
75.81 |
24.07 |
5/31/2022 |
28.88 |
4 |
Earthwork in embankment, cutting and bridge approaches and Construction of minor bridges and RUBs in the section between Beed to Parli form Ch. 167500 to 175000 m for Ahmednagar-Beed-Parli Vaijnath New Broad Gauge line project. |
100 |
3/9/2018 |
27.06 |
18 months |
16.72 |
10.34 |
7/31/2022 |
12.41 |
5 |
Gadag-Wadi New BG Line -Earthwork including blanketing and construction of minor bridges RUB's from KM 210500 to KM 225.150 Between Shahapur (In) to Shirwal (In) Stations |
100 |
3/12/2018 |
45.19 |
18 months |
21.45 |
23.74 |
5/31/2022 |
28.49 |
6 |
Construction of Minor Bridges and Balance Earthwork at isolated locations, Station yards, Side drains, Catch water drain, Toe wall, Pitching etc between Solapurwadi Km 35 to Amalner Km 100 in Ahmednagar - Beed - Parli Vaijnath New BG Line. |
100 |
4/5/2018 |
65.79 |
18 months |
50.43 |
15.36 |
6/16/2022 |
17.66 |
7 |
Secunderabad Division- Proposed new BG line between Badrachalam Road-Sattupalli Stations- Earthwork I Secunderabad Division - Proposed New BG line between Bhadrachalam Road - Sattupalli Stations - Earthwork in embankment to GE-14 specifications and construction of minor bridges and other miscellaneous works from Ch.3720 m to Ch.25100m (between Bhadrachalam Road and proposed Bavannapalem Halt Station) including chord line of 1400m length taking off from existing Dornakal Junction - Bhadrachalam Road-Sattupalli line (Reach-I) |
100 |
6/4/2018 |
51.85 |
12 months |
50.84 |
1.01 |
9/30/2022 |
1.16 |
8 |
Construction of Major Bridges, ROBs including Road approaches from Solapurwdi Km 35 to Amalner km 100 in connection with Ahmednagar Beed Parli Vaijnath New BG Line. |
100 |
7/25/2018 |
60.74 |
18 months |
49.26 |
11.48 |
3/31/2022 |
13.20 |
9 |
Construction of Pipe Distribution Network for Yergaon, Khedi, Bhejgaon Distributories and Babrala, Gadisurla, Bembalchak, Saoli-9,10,11,11 A Minors on Asolamendha Main Canal of Gosikhurd Project |
100 |
9/26/2018 |
80.93 |
12 months |
25.91 |
55.02 |
3/31/2022 |
63.27 |
10 |
Execution of work for design of bridges & building,earthwork in formation,construction of major & minor bridges, service buildings, (S&T) Building,gate goomty,end goomty,OHE Depot,PSI depot,Etc.) Supply of machine crushed stone ballast, transporation of railway materials, P.Way works general electrical works for buildings & stations and other allied works between From Salekesa Station (Including Yard) to Amgaon Station (Excluding Yard) in connection with 3rd BG Railway line between Rajanandgaon-Kalumna stations of Nagpur Division of SEC Railway |
100 |
1/4/2019 |
77.04 |
18 months |
35.86 |
41.18 |
7/31/2022 |
47.36 |
11 |
Execution of work for design of bridges & building,earthwork in formation,construction of major & minor bridges, service buildings, (S&T) Building,gate goomty,end goomty,OHE Depot,PSI depot,Etc.) Supply of machine crushed stone ballast, transporation of railway materials, P.Way works general electrical works for buildings & stations and other allied works between From Tirrora Station (Including Yard) to Gondia Station (Excluding Yard) in connection with 3rd BG Railway line between Rajanandgaon-Kalumna stations of Nagpur Division of SEC Railway |
100 |
1/4/2019 |
77.51 |
18 months |
51.16 |
26.35 |
12/31/2022 |
30.30 |
12 |
Execution of work for design of bridges & building,earthwork in formation,construction of major & minor bridges, service buildings, (S&T) Building,gate goomty,end goomty,OHE Depot,PSI depot,Etc.) Supply of machine crushed stone ballast, transporation of railway materials, P.Way works general electrical works for buildings & stations and other allied works between From Amgaon Station (Including Yard) to Gondia Station (Excluding Yard) in connection with 3rd BG Railway line between Rajanandgaon-Kalumna stations of Nagpur Division of SEC Railway |
100 |
1/10/2019 |
110.57 |
18 months |
48.35 |
62.22 |
12/31/2022 |
71.55 |
13 |
Construction of all civil works upto formation level including dismantling of existing Narrow Gauge line, Earthwork, blanketing, Major & minor bridges, Road Under Bridges (RUB)/ Limited Height Subway (LHS), retaining walls, drains, ground improvement works, cement concrete lining, cross drainage works, relocation of existing roads & utilities, Providing & fixing of Over Head Equipment mast etc. from Chainage 80.00 to Chainage 105.00 km (Total 25 km) in connection with Gauge Conversion Work between Mahuli to Itwari Section in Nagpur Division of South East Central Railway |
100 |
12/6/2019 |
113.85 |
10 Months |
37.14 |
76.71 |
7/31/2022 |
84.38 |
14 |
Construction of Station Building, S&T rooms,COP and Platforms after relocation of service/residental buildings by dismantling and reconstruction including exploration, design and drawings between Belapur to Manmad in connection with Daund-Manmad Doubling Project |
100 |
3/5/2020 |
36.91 |
24 Months |
8.49 |
28.42 |
4/30/2022 |
31.26 |
15 |
Construction of Station Building, S&T rooms,COP and Platforms after relocation of service/residental buildings by dismantling and reconstruction including exploration, design and drawings between Daund to Padhegaon in connection with Daund-Manmad Doubling Project |
100 |
3/5/2020 |
35.93 |
24 Months |
7.94 |
27.99 |
4/30/2022 |
30.79 |
16 |
Construction of all civil works upto formation level including dismantling of existing Narrow Gauge line, Earthwork, blanketing, Major & minor bridges, Road Under Bridges (RUB)/ Limited Height Subway (LHS), retaining walls, drains, ground improvement works, cement concrete lining, cross drainage works, relocation of existing roads & utilities, Providing & fixing of Over Head Equipment mast etc. from Chainage 55.00 to Chainage 80.00 km (Total 25 km) in connection with Gauge Conversion Work between Umred to Mahuli Section in Nagpur Division of South East Central Railway |
100 |
7/22/2020 |
107.21 |
10 Months |
24.97 |
82.24 |
12/31/2022 |
86.35 |
17 |
Construction of Mominpura Road Over Bridge & Limited Height Subway from Panchpawali Bridge to Pahelwan Shah Dargah connecting to Bridge to Bhankheda to Lashkaribagh Area in Nagpur City, at Railway KM 837/39-41 between Nagpur - Kalumna Stations of Nagpur Division |
100 |
09.04.2021 |
132.07 |
12 Months |
2.93 |
129.14 |
12/12/2022 |
129.14 |
18 |
Construction of Road Over Bridges (ROBs) at 4 Locations i.e. Between Umred-Bhiwapur station at LC No. 33- km 1186/10 (Project CH 52735 M) & LC No. 34- km 1187 /30 (Project CH 53262 M) and Between Dighori Buzurg-Itwari Station at LC No. 69- km 1234/655 (Project CH 100138 M) & LC No. 73- km 1237/64 (Project CH 103135 M) in Lieu of LC Gates on Nagbhir- Itwari section in Maharashtra area of Nagpur division |
51 |
18.05.2021 |
35.50 (69.61) |
10 Months |
13.58 |
21.92 |
8/18/2022 |
21.92 |